The WR200 is the smallest of the Wirtgen Group's new generation WR series of cold recyclers. With its proven design and high-end German manufacturing technology, the WR200 guarantees the reliability and durability of the machine and is more flexible and convenient to use.
Project Overview
The Zhangsang Highway on the S228 line of Zhangjiajie City, Hunan Province is an important channel leading to Sangzhi County in the urban area of ​​Zhangjiajie. At present, due to the serious damage to the road surface of some sections, the road sections have been overhauled since the second half of 2017. The length of the repair section is about 10 km. The Wriggen Group's new generation cold recycler WR 200 is used for 20 cm (8 cm original asphalt pavement layer plus 12 cm original part cement stabilized macadam base). The cold recycled layer is used as the lower base layer of the overhauled asphalt pavement structure, and a 20 cm new cement stabilized macadam base layer and a 9 cm asphalt surface layer are placed thereon.
The mechanical equipment used in the construction is shown in the following table:
construction process
Cold recovery unit
Cold regeneration
Steady construction of cold recycling machine
Cold recycled mix
Initial pressure of single steel wheel
Single drum recompression
A cement spreader is used to pre-spread cement on the original road surface as a binder for cold recycled materials. The WR200 cold regenerator pushes the tanker to the local cold regeneration operation at a working speed of 4~6 m/min. The milling and mixing rotor mixes the pre-spreaded cement and the cold regenerator water while milling the 20 cm original pavement material. The accurately added 2.5%~3.5% compacted water of the spray beam is fully stirred to form a cement stabilized cold recycled mixture. The initial reloading of the cold reclaimed mixture was carried out using the Hummer 320 single drum vibratory roller customized by the Wirtgen Group for the Chinese market, followed by shaping with a grader, and then using the Hummer 320 single drum vibratory roller for recompression and the rubber roller compactor. Pressing, the cold recycled layer is finally compacted. Finally, use a sprinkler to sprinkle the cold regenerating layer for no less than 7 days.
Construction effect
Core sample that meets the requirements
Dense core sample
After the cement in-situ cold regeneration layer meets the requirements in the health period, the core sample is sampled, the core sample length meets the design requirements (not less than 20cm), and the core sample has good integrity, compact appearance and uniform distribution of aggregate. The cold regenerative quality of the WR200 was unanimously recognized and praised by the project owner and the construction unit. Under the premise of ensuring timely material supply, normal construction machinery operation and smooth construction process, the WR200 cold recycling machine can complete more than 4,000 m2 of cold regeneration every day. Users who purchased this machine said: “Before you worry about the machine. I bought it small, I didn’t expect its daily workload to be as expected, and the regeneration effect was so good.†(This article is from Wirtgen China)